The National Assembly Standing Committee on Information and Telecommunication has received a report from the Ministry of IT and Telecommunication on the development of the Islamabad Information Technology Park.
The Islamabad Electric Supply Company has authorised the power design for the IT Park, and the Pak Environmental Protection Agency and CDA have granted their no objection certificates (NoC), according to the Ministry of IT and Telecom (IESCO). The transmission line for IT Park has begun construction thanks to IESCO.
A Korean contractor business has reportedly been activated, and the IT park’s site offices are completely operational, according to MoITT. The RCC drain channel has been repaired, and the boundary wall has been upgraded. A 50 kVA Genset has been erected, and IESCO will shortly finish setting up a temporary connection. The ministry claims that the evacuation effort is nearly finished.
The Ministry’s response is that around 120 heaps have been cast in the ground and that the entire pile’s work will be finished by December 31, 2022. The main building’s raft foundation construction will be finished by the end of February 2023. The beginning of construction on basement 2 and completion of basement 1 will be done by the end of June 2023.
To read our blog on “Prices for the 3G and 4G Spectrum Auction will be recommended by MoITT and PTA” click here.